摘要: 水库初期蓄水指从水库开始蓄水至水位达到正常运行水位的整个蓄水期,成功的初期蓄水是水库正常运行的先决因素。目前水库初期蓄水计算一般采用典型年法和长系列法,但受径流年内不完全随机分配的影响,典型年法计算结果偏差较大,而长系列法计算量太大。对此,在2种常用方法基础上创新地提出典型蓄水期、逐月-整体排频2种方法,并选取一个实例使用以上几种方法进行水库初期蓄水计算。通过结果比较分析发现,逐月-整体排频法具有计算量较小且更准确的特点,推荐在类似工程中参考使用。
关键词: 初期蓄水, 逐月排频法, 典型蓄水期法, 逐月-整体排频法, 小中甸水利枢纽工程
Abstract: The reservoir initial storage period refers to the entire period from starting impounding to reaching normal operating level, successful initial water storage is a prerequisite for the successful operation of a reservoir. The reservoir initial storage is generally calculated by using the typical year method and long series method. Influenced by the incomplete random distributed runoff in a year, the calculation result of typical year method has big deviation, while long series method requires too much calculation. Considering these problems and based on the two conventional methods, this article presents two new methods - typical water storage method and month-by-month frequency calculation plus integral frequency calculation method. The two new methods were applied in a case. After comparing the calculation results of the two methods, the later method can reduce calculation and improve accuracy which is recommended to be used in similar projects.
Key words: initial storage, monthly frequency method, typical water storage method, month-by- month frequency calculation plus integral frequency calculation method, Xiaozhongdian water conservancy project
罗纯军,彭娴. 基于径流年内不完全随机分配的水库初期蓄水模型[J]. 人民长江, doi: 10.16232/j.cnki.1001-4179.2018.23.010.
LUO Chunjun,PENG Xian. Storage calculation model for reservoir initial storage based on yearly incomplete random distributed runoff [J]. , doi: 10.16232/j.cnki.1001-4179.2018.23.010.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.rmcjzz.com/CN/10.16232/j.cnki.1001-4179.2018.23.010
http://www.rmcjzz.com/CN/Y2018/V49/I23/54