摘要: 借鉴风电发电同时率指标定义,提出了水电发电同时率概念,即单个或多个水电站可发电量占装机满发电量的比重。利用2016~2018年统调口径水电站逐日入库流量及发电量,计算四川省主要流域2016~2018年水电发电同时率;分析了水电站入库流量与水电发电能力的关系、入库流量与水电发电同时率的关系及流域间水电发电同时率的相关关系。结果表明:(1)四川省2016~2018年3 a平均年水电发电同时率为59%。雅砻江、大渡河、岷江流域年均水电发电同时率超过50%,嘉陵江为40%。(2)四川省各流域代表性水电站入库流量与该流域水电发电能力变化趋势相同。(3)大渡河与岷江、雅砻江与大渡河的水电发电同时率相关系数分别为0.96和0.92,显著高于雅砻江与嘉陵江的相关系数0.65。

关键词: 水电发电同时率; 发电能力; 装机容量; 相关性分析; 四川省;

Abstract: On the basis of the definition of wind power generation simultaneity factor, this paper proposed the concept of hydropower generation simultaneity factor, i.e., the proportion of the generating capacity of hydropower station in the installed generating capacity. The daily inflow and power generation capacity of hydropower stations in Sichuan Province from 2016 to 2018 were used to calculate the hydropower generation simultaneity factor of major river basins in Sichuan Province. The correlations between inflow and hydropower generation capacity, inflow and hydropower generation simultaneity factor, and the hydropower generation simultaneity factor between basins were analyzed. The results showed that:(1) From 2016 to 2018, the annual average hydropower generation simultaneity factor of Sichuan Province was 59%, the annual hydropower generation simultaneity factor of Yalong River, Dadu River and Minjiang River were more than 50%, while that of Jialing River was 40%.(2) The inflow of major hydropower stations and hydropower generating capacity of the whole basin in SichuanProvince showed same trends.(3) The hydropower generation simultaneity factor correlation coefficients between Dadu River and Minjiang River, Yalong River and Dadu River were 0.96 and 0.92 respectively, which was significantly higher than that between Yalong River and Jialing River(0.65).

Key words: hydropower generation simultaneity factor; power generating capacity; installed generating capacity; correlation analysis; Sichuan Province;