基于EPC总承包模式的移民工程建设工期优化思路

刘灿,李先达   

  • 出版日期:2020-05-28 发布日期:2020-05-28

Construction period optimization of resettlement project under EPC general contracting mode

LIU Can, LI Xianda   

  • Online:2020-05-28 Published:2020-05-28

摘要: 基于水电移民工程建设工期控制的行业难点,介绍了水电移民工程传统建管模式和工程建设EPC总承包两种建管模式,并以白鹤滩水电站BM移民安置点项目为例,提出EPC总承包模式下移民工程建设工期的优化措施。分析结果表明:措施实施后,该项目可缩短直线工期,使移民房建工程完成时间满足电站下闸蓄水节点要求,可为水电移民工程建设运用EPC总承包模式提供一些参考。

关键词: 移民工程, 工期优化, EPC, 水电工程

Abstract: This paper introduced the traditional construction mode and the EPC general contracting mode of resettlement project based on difficulty in construction period control for hydropower resettlement project. Taking the BM resettlement site project of Baihetan Hydropower Station as an example, we put forward several optimization measures for its construction period under the EPC general contracting mode. The results showed that the linear construction period of the project can be shortened after the implementation of the measures, and the completion time of the immigration housing project could meet the requirement of the power station. The results provide a reference for the EPC general contracting mode in the construction of hydropower immigration project.

Key words: resettlement project, construction period optimization, EPC, hydropower project;