摘要: 投资控制是工程建设项目管理的重要内容,只有将投资控制管理融入到工程项目的各个阶段,才能最大限度地提高水电站工程项目的投资效益。介绍了杨房沟水电站公路工程建设过程中,参建各方根据工程项目的设计、采购、施工、完工阶段的不同特点,所采取的不同投资控制方法;详细分析了各阶段参建各方在投资控制中的角色定位及作用,以及应关注的重点。相关结果可为类似工程建设管理提供参考。
关键词: 公路工程, 灾害治理, 投资控制, 设计变更, 合同管理, 杨房沟水电站
Abstract: Investment control plays a critical role in the management of project construction. Only by incorporating investment controlling in every phase of a project can maximize returns of investing a hydropower project. In the access road construction, the project stakeholders adopt different investment controlling measures based on the characteristics of design, procurement, construction and completion phases. We analyze every stakeholder’s role and impact in the investment controlling and identify what aspects they need to pay more attention to.
Key words: road engineering, disaster management, investment control, design change;contract management, Yangfanggou Hydropower Station
李锦成,孙贵金,孙鹏辉. 杨房沟水电站公路工程投资控制方法浅析[J]. 人民长江, doi: 10.16232/j.cnki.1001-4179.2018.24.006.
LI Jincheng, SUN Guijin, SUN Penghui. Analysis of investment control method for access road project of Yangfanggou Hydropower Station[J]. , doi: 10.16232/j.cnki.1001-4179.2018.24.006.