摘要: 山区风电场因地形条件有限,在勘察设计时考虑因素较多,鉴于此,结合山区风电场的特点及具体工程实例,从机组选型及微观选址、现场地质勘察手段、复杂地形条件下交通运输方案的设计拟定等方面,对山区风电场的设计难点和设计思路进行了总结。工程实例表明,在设计中只要充分考虑上述因素,就可以完成山区风电场的勘察设计工作。
关键词: 风电场, 机组选型, 运输方案, 工程设计, 山区
Abstract:
Due to the limitation of topography, many factors should be considered in the survey and design of mountainous wind power field. For this reason, in the combination of the characteristics of wind power field and the concrete engineering case, the difficulties and thoughts in the design of wind power field in mountainous area are summarized from the aspects of unit type selection, specific site selection, field geological surveying means, transportation scheme design under complex topography etc. Engineering case shows that if the abovementioned factors are fully considered in the design, the survey and design of wind power field in mountainous area can be done well.
Key words: wind power site selection, unit type selection, transportation scheme, engineering design, mountainous wind power field
陶铁铃 付文军 陈玉梅. 山区风电场设计难点及对策[J]. 人民长江, doi: 10.16232/j.cnki.1001-4179.2015.18.006.